The Fruit Shack - second thing after site access. Good place to get out of the rain, sleep, stage equipment….. This was a 12x12 platform later covered with a roof. None of the boards were really cut. The idea being this 12’ material could be re used for the cabin build. Screws were used to aid in disassembly. This project occurred on 11-30-2018. A metal roof was added on Xmas weekend the following month.
Russ clearing the road with leaf blower. Picture taken from van. Almost stuck in place….
This is the start of the deck. This became the only flat spot on the site.
The tailgate tents don’t really work, maybe for sun, but they really don’t shed rain very well.
December 25th, 2018 The tailgate tent idea did not work - began construction of roof.
Under Construction, the tarps really help to stop the wind at sitting and sleeping level.
Kevin, one of the first workers.
Completed. We added the front shed roof, and it was immediately dubbed the “the Fruit Shack”